Item Coversheet
 CITY OF PLANO
COUNCIL AGENDA ITEM
Council Meeting Date:  10/25/2016

Department:  Engineering

Department Head: B. Caleb Thornhill

Agenda Coordinator:  Libby McCabe

CAPTION


To Tiseo Paving Co., increasing the contract by $117,082 for the Windhaven Parkway project, Change Order No. 3.  Original Bid No. 2015-015-B. APPROVED


FINANCIAL SUMMARY

 

CIP

FISCAL YEAR:


2016-17

Prior Year
(CIP Only)

Current
Year

Future
Years


TOTALS

Budget

1,016,176

350,625

0

1,366,801

Encumbered/Expended Amount

-1,016,176

-233,543

0

-1,249,719

This Item

0

-117,082

0

-117,082

BALANCE

0

0

0

0



FUND(S):  Street Improvements CIP



 


COMMENTS:  Funding is available for this item in the 2016-17 Street Improvements CIP.  This third change order to the existing construction contract, in the amount of $117,082, will utilize the remaining funding for this project.  Future expenditures on this project will need to be offset by savings from other Street Improvement projects or future appropriations.

SUMMARY OF ITEM


See Recommendation Memorandum.

Strategic Plan Goal:

Financially Strong City with Service Excellence

Plano Tomorrow Plan Pillar:

Built Environment

 


ATTACHMENTS:
DescriptionUpload DateType
Recommendation Memo10/17/2016Memo
Location Map10/12/2016Map