  CITY COUNCIL AGENDA MEMO
MEETING DATE: 8/25/2025
DEPARTMENT:Engineering-CIP
DIRECTOR:B. Caleb Thornhill, P.E., Director of Engineering
AGENDA ITEM:

Award RFB No. 2025-0372-B in the amount of $2,594,104 for Intersection Improvements – Legacy Drive & SH 121 (Site 1), SH 121 at JP Morgan Driveway (Site 2), Corporate Drive & Legacy Drive (Site 3), Corporate Drive & Tennyson Parkway (Site 4), Project No. ENG-S-00003

RECOMMENDED ACTION:Award/Rejection of Bid/Proposal

ITEM SUMMARY

RFB No. 2025-0372-B for Intersection Improvements – Legacy Drive & SH 121 (Site 1), SH 121 at JP Morgan Driveway (Site 2), Corporate Drive & Legacy Drive (Site 3), Corporate Drive & Tennyson Parkway (Site 4), Project No. ENG-S-00003, for the Engineering Department to XIT Paving and Construction, Inc. in the amount of $2,594,104; and authorizing the City Manager to execute all necessary documents. Approved

 

 

BACKGROUND

The Engineering Department opened bids on July 15, 2025, for Intersection Improvements – Legacy Drive & SH 121 (Site 1), SH 121 at JP Morgan Driveway (Site 2), Corporate Drive & Legacy Drive (Site 3), Corporate Drive & Tennyson Parkway (Site 4), Project No. ENG-S-00003. The project includes the addition of turn lanes, accessibility upgrades, signal updates, and geometric modifications to improve safety or reduce congestion.

 

1. Legacy Drive & SH 121 (Site 1) - Additional northbound right turn lane

2. SH 121 at JP Morgan Driveway (Site 2) - Northbound frontage road existing turn lane extension

3. Corporate Drive & Legacy Drive (Site 3) - Additional eastbound right turn lane and eastbound/westbound dual left turn lanes

4. Corporate Drive & Tennyson Parkway (Site 4) - Additional eastbound dual left turn lanes

 

The lowest responsive and responsible bid was submitted by XIT Paving and Construction, Inc. in the amount of $2,594,104. There were a total of 2,498 vendors notified of this project. Four (4) complete bids were received for the project as shown in the attached bid recap.

 

If this project is not awarded, traffic congestion and delays would continue to increase, and vehicular and pedestrian safety would continue to be reduced, resulting in a reduction in the quality of life for citizens and motorists at these locations.

FINANCIAL SUMMARY/STRATEGIC GOALS

Funding for this item is budgeted in the 2024-25 Street Improvements CIP and is planned for future years as well. Construction services for Intersection Improvements – Legacy Drive & SH 121 (Site 1), SH 121 at JP Morgan Driveway (Site 2), Corporate Drive & Legacy Drive (Site 3), Corporate Drive & Tennyson Parkway (Site 4), Project No. ENG-S-00003, in the total amount of $2,594,104 will leave a current year balance of $75,350 for future expenditures.

 

Approval of this item will support the City's Strategic Plan Critical Success Factor of being an Excellent, Innovative, and Accountable City Government.

ATTACHMENTS:
DescriptionUpload DateType
Bid Recap8/7/2025Bid Recap
Location Map8/1/2025Map