CAPTION


Bid No. 2017-0438-B for Carpenter Park - Coit Road Traffic Signal, Project No. 6638, to Rebcon, Inc. in the amount of $381,620; and authorizing the City Manager to execute all necessary documents. Approved


FINANCIAL SUMMARY

 

CIP
FISCAL YEAR: 2016-17      Prior Year
(CIP Only)

Current

Year

Future

Years

TOTALS
Budget  241,136  3,368,505 3,820,000 7,429,641
Encumbered/Expended Amount  -241,136 -513,168 0 -754,304
This Item  0 -381,620  0 -381,620
Balance   0 2,473,717  3,820,000  6,293,717



FUND(S):  Park Improvement CIP



 


COMMENTS:  

Funding for this item is available in the 2016-17 Park Improvement CIP.  Installation of a traffic signal at Carpenter Park and Coit Road, in the amount of $381,620, will leave a current year balance of $2,473,717 available for other Recreational Trail projects in the future.


SUMMARY OF ITEM


Staff recommends the bid received from Rebcon, Inc. in the amount of $381,620 be accepted as the lowest responsible bid conditioned upon timely execution of any necessary contract documents.

 

The $381,620 award includes installation of a traffic signal, a new left-turn lane, relocation of the bike trail/pedestrian crossing, and new accessible trail ramps.

   

The low bid of $381,620 exceeds the construction estimate of $350,000.  Three bids were received.  Staff does not believe that rebidding the project will result in lower bids.   Project funding is available to award a contract based on the actual bids received.



Strategic Plan Goal:

Financially Strong City with Service Excellence, Safe Large City

Plano Tomorrow Plan Pillar:

Built Environment, Social Environment

 


ATTACHMENTS:
DescriptionUpload DateType
Location Map7/12/2017Map
Bid Recap7/12/2017Bid Recap