Item Coversheet
 CITY OF PLANO
COUNCIL AGENDA ITEM
Council Meeting Date:  9/10/2018

Department:  Engineering-Facilities

Department Head: B. Caleb Thornhill

Agenda Coordinator:  Michael Parrish x7554

CAPTION


RFB No. 2018-0479-B for the Municipal Center Restroom Renovations to KC Construction Services, Inc. in the amount of $449,704; and authorizing the City Manager to execute all necessary documents. Approved


FINANCIAL SUMMARY

 

CIP
FISCAL YEAR:  2018-19   Prior Year
(CIP Only)

Current

Year

Future

Years

TOTALS
Budget  1,147,203  2,602,042 1,900,000 5,649,245
Encumbered/Expended Amount  -1,147,203 -1,740,997 0 -2,888,200
This Item  0 0  -449,704 -449,704
Balance   0 861,045  1,450,296  2,311,341



FUND(S):  Capital Maintenance Fund



 


COMMENTS:  Funding is available for this item in the 2017-18 Capital Maintenance Fund budget and will be carried forward into the 2018-19 fiscal year. Construction services for the Municipal Center Restroom Renovations projects, in the amount of $449,704, will leave a total balance of $2,311,341 available for future expenditures at the Plano Municipal Center or other city facilities.

SUMMARY OF ITEM


See Recommendation Memo.

Strategic Plan Goal:

Financially Strong City with Service Excellence

Plano Tomorrow Plan Pillar:

Built Environment

 


ATTACHMENTS:
DescriptionUpload DateType
Recommendation Memo9/4/2018Memo
Bid Recap8/29/2018Bid Recap