Item Coversheet
  CITY COUNCIL AGENDA MEMO
MEETING DATE: 4/27/2020
DEPARTMENT:Public Works
DIRECTOR:Dan Prendergast, Assistant Director of Public Works
AGENDA ITEM:Approve RFB No. 2020-0385-B in the amount of $1,249,850 for sanitary sewer manhole lining for the Sanitary Sewer Manhole Lining Project - 2020, Project No. 7180
RECOMMENDED ACTION:Award/Rejection of Bid/Proposal

ITEM SUMMARY

RFB No. 2020-0385-B for the Sanitary Sewer Manhole Lining Project - 2020, Project No. 7180, for Public Works Department to Infrastructure Rehabilitation USA, Inc. in the amount of $1,249,850; and authorizing the City Manager to execute all necessary documents. Approved

BACKGROUND

Public Works recommends the bid for the Sanitary Sewer Manhole Lining Project - 2020 project to be awarded to Infrastructure Rehabilitation USA, Inc., in the amount of $1,249,850, to be accepted as the lowest responsible bid for the project conditioned upon timely execution of all necessary documents.

 

The project involves the lining of 1,890 vertical feet in sewer manholes to prevent infiltration and restore structural strength in 184 sanitary sewer manholes at various locations throughout the City of Plano.

 

Engineer's estimate for this project is $1,318,000.

 

If not awarded, the sanitary sewer manholes will not be lined, allowing for the possibility of infiltration and structural damage.

FINANCIAL SUMMARY/STRATEGIC GOALS

Funding for this item is available in the 2019-20 Sewer CIP and is expected in 2020-21.  The contract for the Sanitary Sewer Manhole Lining project, in the total amount of $1,249,850, will leave a current year balance of $30,000 available for future project expenditures.       

 

Approval of this item will support the City's Strategic Plan Critical Success Factor of being an Excellent, Innovative, and Accountable City Government and meets the Plano Tomorrow Pillar of Built Environment.        

 

FINANCIAL SUMMARY/STRATEGIC GOALS

Funding for this item is available in the 2019-20 Sewer CIP and is expected in 2020-21.  The contract for the Sanitary Sewer Manhole Lining project, in the total amount of $1,249,850, will leave a current year balance of $30,000 available for future project expenditures.       

 

Approval of this item will support the City's Strategic Plan Critical Success Factor of being an Excellent, Innovative, and Accountable City Government and meets the Plano Tomorrow Pillar of Built Environment.        

 

ATTACHMENTS:
DescriptionUpload DateType
Bid Recap3/30/2020Bid Recap