CITY COUNCIL AGENDA MEMO |
|
| | | | | | | | MEETING DATE: | 6/28/2021 | DEPARTMENT: | Engineering-CIP | DIRECTOR: | B. Caleb Thornhill, P.E., Director of Engineering | AGENDA ITEM: | Approve an increase in the amount of $55,836 for engineering professional services 17th Street Paving and Waterline Improvements, Project No. 7222. | RECOMMENDED ACTION: | Approval of Contract Modification |
|
| | | | | | | | ITEM SUMMARY To approve an increase to the current awarded contract amount of $345,300 by $55,836, for a total contract amount of $401,136, for additional easement documents for 17th Street Paving and Waterline Improvements, Project No. 7222, from Freese and Nichols, Inc. for the Engineering Department; and authorizing the City Manager to execute all necessary documents. (Contract No. 2020-0309-X; Modification No. 1) Approved |
| | | | | | | | PREVIOUS ACTION/PRESENTATION On 2/10/2020, City Council approved the expenditure of professional engineering services for 17th Street Paving and Waterline Improvements, Project No. 7222, in the amount of $345,300 to Freese and Nichols, Inc. |
| | | | | | | | BACKGROUND The Engineering Department recommends approval of Contract Modification No. 1 for the increase in the professional services agreement with Freese and Nichols, Inc, in the amount of $55,836, for the 17th Street Paving and Waterline Improvements, Project No. 7222.
Contract Modification No. 1 includes survey and preparation of twenty-two (22) additional sidewalk easement documents required for the 17th Street Paving and Waterline Improvements project.
If this contract modification is not approved, right-of-way constraints would prohibit the city from replacing and/or maintaining the existing ADA non-compliant sidewalk, resulting in accessibility and safety concerns for pedestrians utilizing the existing, deteriorating, sidewalk. |
| | | | | | | | FINANCIAL SUMMARY/STRATEGIC GOALS Funding for this item is available in the 2020-21 Street Improvements CIP. The first modification to the existing professional services agreement, in the total estimated amount of $55,836, will leave a current year balance of $269,474 for future project expenditures.
Approval of this item will support the City's Strategic Plan Critical Success Factor of being an Excellent, Innovative, and Accountable City Government. |
ATTACHMENTS: | Description | Upload Date | Type | Location Map | 6/15/2021 | Map |
|
|