Item Coversheet
  CITY COUNCIL AGENDA MEMO
MEETING DATE: 6/28/2021
DEPARTMENT:Engineering-CIP
DIRECTOR:B. Caleb Thornhill, P.E., Director of Engineering
AGENDA ITEM:Approve an increase in the amount of $55,836 for engineering professional services 17th Street Paving and Waterline Improvements, Project No. 7222.
RECOMMENDED ACTION:Approval of Contract Modification

ITEM SUMMARY

To approve an increase to the current awarded contract amount of $345,300 by $55,836, for a total contract amount of $401,136, for additional easement documents for 17th Street Paving and Waterline Improvements, Project No. 7222, from Freese and Nichols, Inc. for the Engineering Department; and authorizing the City Manager to execute all necessary documents. (Contract No. 2020-0309-X; Modification No. 1) Approved

PREVIOUS ACTION/PRESENTATION

On 2/10/2020, City Council approved the expenditure of professional engineering services for 17th Street Paving and Waterline Improvements, Project No. 7222, in the amount of $345,300 to Freese and Nichols, Inc.

BACKGROUND

The Engineering Department recommends approval of Contract Modification No. 1 for the increase in the professional services agreement with Freese and Nichols, Inc, in the amount of $55,836, for the 17th Street Paving and Waterline Improvements, Project No. 7222.

 

Contract Modification No. 1 includes survey and preparation of twenty-two (22) additional sidewalk easement documents required for the 17th Street Paving and Waterline Improvements project.

 

If this contract modification is not approved, right-of-way constraints would prohibit the city from replacing and/or maintaining the existing ADA non-compliant sidewalk, resulting in accessibility and safety concerns for pedestrians utilizing the existing, deteriorating, sidewalk.

FINANCIAL SUMMARY/STRATEGIC GOALS

Funding for this item is available in the 2020-21 Street Improvements CIP.  The first modification to the existing professional services agreement, in the total estimated amount of $55,836, will leave a current year balance of $269,474 for future project expenditures.

 

Approval of this item will support the City's Strategic Plan Critical Success Factor of being an Excellent, Innovative, and Accountable City Government. 

ATTACHMENTS:
DescriptionUpload DateType
Location Map6/15/2021Map