Item Coversheet
  CITY COUNCIL AGENDA MEMO
MEETING DATE: 8/23/2021
DEPARTMENT:Engineering-CIP
DIRECTOR:B. Caleb Thornhill, P.E., Director of Engineering
AGENDA ITEM:Award of a bid in the amount of $2,997,792 for Legacy Drive Corridor Improvements, Project No. 6069.1.
RECOMMENDED ACTION:Award/Rejection of Bid/Proposal

ITEM SUMMARY

RFB No. 2021-0389-B for Legacy Drive Corridor Improvements, Project No. 6069.1, for the Engineering Department to Urban Infraconstruction, LLC in the amount of $2,997,792; and authorizing the City Manager to execute all necessary documents. Approved

BACKGROUND

The Engineering Department opened bids on July 15, 2021 for the Legacy Drive Corridor Improvements project. The project includes construction of capacity and intersection improvements at three (3) intersections along Legacy Drive corridor: Independence Parkway, Custer Road, and K Avenue.  Each intersection has proposed dual left turn lanes, dedicated right turn lanes, and additional thru lanes as needed to maximize the capacity at each intersection.  Signal modifications will be completed, as well, to adjust capacity improvements.

 

The lowest responsive and responsible bid was submitted by Urban Infraconstruction, LLC, in the amount of $2,997,792.  There were a total of 780 vendors notified of this project. Eight (8) complete bids were received for the project as shown in the attached bid recap.

 

If this project is not awarded, the result will be continued traffic congestion and deterioration of the existing pavement at the three intersections, resulting in increased future maintenance and having a negative impact on the quality of life for motorists in these areas.

FINANCIAL SUMMARY/STRATEGIC GOALS

Funding for this item is available in the 2020-21 Street Improvements CIP and is planned for future years, as well.  Construction services for the Legacy Drive Corridor Improvements project, in the total estimated amount of $2,997,792, will leave a current year balance of $329,302 for future project expenditures.

 

Approval of this item will support the City's Strategic Plan Critical Success Factor of being an Excellent, Innovative, and Accountable City Government. 

ATTACHMENTS:
DescriptionUpload DateType
Bid Recap8/10/2021Bid Recap
Location Map8/16/2021Map