Item Coversheet
  CITY COUNCIL AGENDA MEMO
MEETING DATE: 5/23/2022
DEPARTMENT:Engineering
DIRECTOR:B. Caleb Thornhill, P.E., Director of Engineering
AGENDA ITEM:A Resolution to approve the terms and conditions of a Local Project Advance Funding Agreement for reconstruction  between City of Plano and the Texas Department of Transportation (TxDOT) for improvements on W. Parker Road at Pittman Creek.
RECOMMENDED ACTION:Adoption of Resolutions

ITEM SUMMARY

Resolution No. 2022-5-9(R): To approve the terms and conditions of a Local Project Advance Funding Agreement (LPAFA) between the City of Plano and the Texas Department of Transportation (TxDOT) for the bridge replacement on W. Parker Road at Pittman Creek; authorizing the City Manager to take such action and execute such documents as necessary to effectuate the agreement herein; and providing an effective date. Adopted

BACKGROUND

TxDOT informed the City of Plano January 2022 that the W. Parker Road culvert system at Pittman Creek had been selected as apart of the Highway Bridge Program (HBP) for a complete replacement.  The HBP is a federal-aid program that provides funding to enable states to improve the condition of highway bridges through replacement, rehabilitation and systematic preventive maintenance. 

The W. Parker Road at Pittman Creek location was selected based on its latest inspection including:

-        Built in 1970’s

-        Ranked: Poor, Sufficiency Rating 34.9

-        Culvert Rating: 4 – Large Spalls, heavy scaling, wide cracks

 

The HBP funding is as follows: 80% federal, 10% TxDOT and 10% local funds.  The City’s estimated participation is $135,286.  The anticipated schedule will be as follows:

-        Scope – 2/2022 – COMPLETE

-        Funding commitment 5/2022 – PENDING RESOLUTION CONSIDERATION

-        AFA execution – December 2022

-        Design start – July 2023

-        Construction start – July 2025

FINANCIAL SUMMARY/STRATEGIC GOALS

Funding for this item is available in the 2021-22 Street Improvement CIP.  The total estimated amount to be spent for the City's participation in the Local Project Advance Funding Agreement for the bridge replacement on W. Parker Road at Pittman Creek is $135,286.  

 

Approval of this item will support the City's Strategic Plan Critical Success Factor of being an Excellent, Innovative, and Accountable City Government.

ATTACHMENTS:
DescriptionUpload DateType
Resolution5/12/2022Resolution
Exhibit A4/29/2022Exhibit
Parker Rd Bridge Replacement4/6/2022Map