Item Coversheet
  CITY COUNCIL AGENDA MEMO
MEETING DATE: 6/13/2022
DEPARTMENT:Engineering-Facilities
DIRECTOR:B. Caleb Thornhill, P.E., Director of Engineering
AGENDA ITEM:Approval of an increase in the amount of $332,625 for Municipal Center - City Council Chambers Renovations, Project No. 7364
RECOMMENDED ACTION:Approval of Contract Modification

ITEM SUMMARY

To approve an increase to the current awarded contract amount of $40,000 by $332,625, for a total contract amount of $372,625, for Municipal Center - City Council Chambers Renovations, Project No. 7364, from Brinkley Sargent Wiginton Architects, Inc.; and authorizing the City Manager to execute all necessary documents.  (Contract Modification No. 1) Approved

PREVIOUS ACTION/PRESENTATION

On July 12, 2021, the City entered into an agreement for the Municipal Center - City Council Chambers Renovations, Project No. 7364 with Brinkley Sargent Wiginton Architects, Inc. in the amount of $40,000.

BACKGROUND

The Engineering Department recommends approval of Contract Modification No. 1 for the increase in the Professional Services Agreement dated July 12, 2021, with Brinkley Sargent Wiginton Architects, Inc. a Texas Corporation, in the amount of $332,625, for the Municipal Center - City Council Chambers Renovations, Project No. 7364.

 

Contract Modification No. 1 includes additional services for design development and construction documents including bid services and construction administration for the following design disciplines: architectural, technology systems, structural, mechanical, electrical, and plumbing engineering services.  It will also add the following consulting services: accessibility, commissioning, interior design, and furniture selection/procurement. 

 

Brinkley Sargent Wiginton Architects, Inc. was contracted to develop schematic designs and renderings for the concepts used for project scoping and community engagement for Municipal Center - City Council Chambers Renovations.

 

If this contract modification is not approved, the project would be delayed by a considerable amount costing additional project funds due to monthly cost escalations.

FINANCIAL SUMMARY/STRATEGIC GOALS

Funding for this item is available in the 2021-22 Municipal Facilities CIP.  The first modification to the Professional Services Agreement for design development and construction documents, in the total estimated amount of $332,625, will leave a current year balance of $157,375 for future expenditures.

 

Approval of this item will support the City's Strategic Plan Critical Success Factors of being an Excellent, Innovative, and Accountable City Government. 

 