  CITY COUNCIL AGENDA MEMO
MEETING DATE: 6/13/2022
DEPARTMENT:Parks
DIRECTOR:Ron Smith, Director of Parks and Recreation
AGENDA ITEM:Approve an expenditure in the amount of $250,000 for landscape architect professional services for Horseshoe Park Renovation, Project No. 7499
RECOMMENDED ACTION:Approval of Expenditure

ITEM SUMMARY

To approve an expenditure for landscape architect professional services for Horseshoe Park Renovation, Project No. 7499, in the amount of $250,000 from JBI Partners, Inc. for the Parks and Recreation Department; and authorizing the City Manager to execute all necessary documents. Approved

BACKGROUND

The last playground and park infrastructure update at Horseshoe Park dates back to 1995 placing existing features at 27 years old. The renovation at this location will include replacement of the playground, irrigation system and drinking fountain. It will also address ADA accessibility issues to update barrier free ramps and complete sidewalk connections as well as renovate the cricket pitch, lighting, site grading and sod.

 

JBI Partners, Inc. was deemed most qualified based on their Statement of Qualifications submission for RFQ No. 2021-0380-XR. The contract fee is $250,000 for landscape architect professional services which includes site analysis, a master plan developed with public input, topographic surveying, geotechnical services, preliminary design, sealed construction documents, Texas Accessibility Standards review, bid phase services, and construction phase services.

 

The benefit of this project includes updating park infrastructure that is beyond its life span, leveling and re-grassing uneven athletic surfaces, providing accessibility updates and the possibility of converting unused backstop space into an open drop-in practice space. Not approving the expenditure would result in the park amenities continuing to age in place with an increased demand for maintenance or, potentially, the loss of feature functionality.

 

The design process for Horseshoe Park Renovations is estimated to be completed in 2023. The project will then be released for bidding. Bids will be reviewed, an offeror will be selected and a bid award is anticipated to need Council action in 2023.

FINANCIAL SUMMARY/STRATEGIC GOALS

Funding for this item is available in the 2021-22 Park Improvements CIP and is planned for 2022-23, as well. Professional services for the Horseshoe Park Renovation project, in the total estimated amount of $250,000, will leave a current year balance of $47,000 for future project expenditures.

 

Approval of this item will support the City's Strategic Plan Critical Success Factor of being an Excellent, Innovative, and Accountable City Government. 

FINANCIAL SUMMARY/STRATEGIC GOALS

Funding for this item is available in the 2021-22 Park Improvements CIP and is planned for 2022-23, as well. Professional services for the Horseshoe Park Renovation project, in the total estimated amount of $250,000, will leave a current year balance of $47,000 for future project expenditures.

 

Approval of this item will support the City's Strategic Plan Critical Success Factor of being an Excellent, Innovative, and Accountable City Government. 

ATTACHMENTS:
DescriptionUpload DateType
Location Map5/26/2022Map