MEETING DATE: 6/12/2023
DEPARTMENT:Engineering-Facilities
DIRECTOR:B. Caleb Thornhill, P.E., Director of Engineering
AGENDA ITEM:Award of bid in the amount $398,390 for 2022-0624-B Municipal Center Cooling Tower Project No. 7407.
RECOMMENDED ACTION:Award/Rejection of Bid/Proposal

ITEM SUMMARY

RFB No. 2022-0624-B for Municipal Center Cooling Tower, Project No. 7407, for the Engineering Department to Synergy Environmental Services, L.L.C. in the amount of $398,390; and authorizing the City Manager to execute all necessary documents. Approved

BACKGROUND

The Purchasing Department solicited a bid for Cooling Tower. Six (6) responses were received.

 

The Engineering Department opened bids on April 25, 2023 for the Municipal Center Cooling Tower. The project includes all labor, equipment, materials and supervision as required by the specifications and drawings.

 

The lowest responsive and responsible bid was submitted by Synergy Environmental Services, L.L.C. in the amount of $398,390.00

 

The existing cooling tower is over 15 years old and is at the end of its life expectancy and has deteriorated such that replacement is required.

 

The funding for the project is in Project FAC-F-7407 Capital Maintenance Fund account 54527.

FINANCIAL SUMMARY/STRATEGIC GOALS

Funding for this item is available in the 2022-23 Capital Maintenance Fund.  Replacement of the Municipal Center Cooling Tower, in the total estimated amount of $398,390, will leave a current year balance of $810 for future project expenditures.

 

This item supports the City's Strategic Plan Critical Success Factor of being an Excellent, Innovative, and Accountable City Government.